Security Lighting 2018-06-26T06:16:12+00:00
NoProjectCommencement DateStatus
1Supply Installation, Testing and Commissioning of Street and Security Lighting in Juja, Thika and Ruiru22nd April 2015100% Works of the works completed,
DLP ended on 28th February, 2017
2Supply Installation and Commissioning of Street and Security Lighting in Kiambu and Karuri15thApril 2015100% Works of the works completed,

DLP ended on 28thJanuary, 2017
3Supply Installation and Commissioning of Street and Security Lighting in Limuru and Kikuyu4thMay 2015100% Works of the works completed,

DLP ended on 28thFebruary, 2017
4Supply Installation and Commissioning of Street and Security Lighting in Tala/Kangundo and Mavoko14thApril 2015100% Works of the works completed,
DLP ended on 14th February, 2017
5Supply Installation and Commissioning of Street and Security Lighting in Kitengela, Ngong and Ongata Rongai13th April 2015100% Works of the works completed,
DLP ended on 10th February, 2017
6Supply Installation and Commissioning of Street and Security Lighting Lot 1 Nairobi County6thJuly 2015100% Works of the works completed,
DLP ended on 10thMay, 2017
7Supply Installation and Commissioning of Street and Security Lighting Lot 2 Nairobi County21st April2015100% Works of the works completed,
DLP ended on 21st January, 2017
8Supply Installation and Commissioning of Street and Security Lighting Lot 3 Nairobi County16TH July 2015100% Works of the works completed,
DLP ended on 20stApril, 2017